Commissioning CostsExpectations for Animal and BSL Facilities Published November 2005
What percentage of total construction will commissioning cost you?
Commissioning an animal facility is an essential part of project success. The cost of commissioning is estimated at ¾% to 1.5% of cost of construction. For a BSL facility, expect 4-5% of construction cost. The cost of commissioning cost is in addition to cost of start up. - From Tradeline's Animal Research Facilities 2005 Conference |