In construction contract
terminology, these are changes ordered by the owner consisting of
additions, deletions or other revisions within the general scope of the
contract. The contract sum and the contract time are adjusted
accordingly. All changes in the work, except those of a minor nature not
involving an adjustment to the contract sum or the contract time, should
be authorized by change order.