Stanford University Installs Advanced Power System Protection
Palo Alto, CA--October 2004--To provide a stable electric power supply and meet the burgeoning demands of the 21st century, Stanford University recently upgraded its primary distribution substation and reconfigured controls to enable a power island via the existing campus cogeneration system.
Located beside Palo Alto, Calif., in the San Francisco Bay area, Stanford University is more than a medium-size city unto itself—it is a highly developed and complex campus with facilities and services that are far more elaborate and strategic than those of the typical community of 13,000. Yet, with a profusion of research and medical centers, plus housing, classrooms, sports, cultural and shopping complexes, it is one of the most energy-efficient institutions among California's research universities.
The ever-mounting electric energy needs of "The Farm," as the 8,200-acre Stanford campus is known, include providing for a vigorous real estate development plan. There are 678 major buildings at Stanford (12.6 million sf total), plus 843 owner-occupied housing units for faculty on campus, and 628 rental units. The local county Board of Supervisors has approved a new, 10-year University General Use Permit and Community Plan allowing for two million additional square feet of academic facilities and up to 3,000 new housing units to be built on campus. When the plan is fully implemented, The Farm will house thousands of buildings and an even higher population of users who will be highly dependent on reliable electric power.
A 50 MW gas and steam turbine cogen system, operated by Cardinal Cogeneration, meets much of the University's present power needs, and also sells power back to the general grid via Pacific Gas & Electric Company (PG&E), backfeeding an average of approximately 20 MW. The faculty residential area is served by PG&E. The Stanford Medical Center, located within Palo Alto city limits, gets its power from that city.
The campus's main distribution substation was built by PG&E in the 1950s, and purchased by the University in the mid-1980s.
Glyn Lewis, partner and design engineer for Applied Power, a Redwood Shores, Calif., electrical engineering consultant, was hired by the Stanford High Voltage Shop, which runs the Electrical Power System, to perform a peer review of the substation in 2002. Lewis and the High Voltage Shop organization decided that much of the main substation's hardware would have to be replaced or upgraded to meet future goals. Also, the Utility Group needed to modify relay protection and communications to implement the power island. The project team divided the work into two phases, and Lewis was retained as a consulting engineer for the project.
Phase One began with replacement of the substation circuit breakers and disconnect switches. "The circuit breakers had to be replaced. They were 50 years old, and there were no spare parts available anymore," Lewis explains. "Secondly, the Utility Group was experiencing trouble with the high-voltage disconnect switches, so they wanted to have those replaced for reasons of safety as well as reliability."
"We split the substation so that we'd have most of it operating during the upgrade," explains Steve Briscombe, Stanford electric utility manager. "We decommissioned one side of the bus and replaced the protection relays, then finished up on the other side. This approach enables us to accomplish the whole project without shutting down University facilities."
The old 60 kV OCBs (oil-filled circuit breakers) were removed from the substation, and replaced with SF6 (sulfur hexafluoride gas) breakers. "We also added potential transformers and isolation switches, and did some major rearranging in the bus structures of the substation," says Lewis. "In conjunction with that, we upgraded the old relay and control panels, with relays from SEL (Schweitzer Engineering Laboratories, Pullman, Wash.).
The new relays include the SEL-351 Directional and Overcurrent Reclosing Relay (4 units), SEL-311 Series Relay (4 units), SEL-551 Overcurrent/Reclosing Relay (2 units), and SEL-587 Current Differential Relay (2 units). There are also redundant SEL-2100 Logic Processor units to apply the SEL logic and communications. SEL-2505 Remote I/O Modules handle the fiber optics link for remote control from the cogeneration plant, which is 2,000 feet away from the control room.
"In general, SEL relays are my preference," says Lewis. "One of the main reasons is the support that I get from the Schweitzer personnel. They are very responsive, not only the people at headquarters but also the field personnel." In the initial design support was provided by Brad Heilman of SEL and Jim Flanagan of Tarbell Associates. Lewis adds that another factor in his choice of SEL equipment was because of the array of features available in a single relay, and the fact that SEL relays meet the "utility grade" requirements of PG&E.
The relays and control system are fully redundant (a PG&E requirement for multi-functional relaying), with all of the outputs configured in parallel and programmed identically. They feed into dual SEL-2100 Logic Processors. The SEL-2100s retrieve device status and remote system information using MIRRORED BITS® communications and provides them with optional I/O using SELOGIC® control equations to implement advanced protection and control.
"The SEL-2100s perform the function of the bus differential scheme and for splitting the bus," Lewis says. "Basically we have a dual-feed bus, but it doesn't have a tie breaker. Instead, it has disconnect switches, including a motor-operated load break switch and a couple of other disconnect switches in series with it."
Lewis says the project team was able to create two zones of bus differential just by putting those switches into the SEL-2100 and then automatically convert a single zone to a double zone. "That was a neat feature," he adds.
"One of the values of doing it this way is that all the CT ratios are different," Lewis continues, "so I was able to create this bus differential scheme using the SELOGIC. I fully tested it before it shipped out from the supplier to prove that the bus differential scheme works. The SELOGIC and SEL-311s and SEL-351s all talking to each other makes this possible."
Digital synchroscopes were added to the substation controls, and the SCADA system, which is used solely to monitor substation status, was revamped. The remote control from the cogen plant, located 2,000 feet from the substation control room, was installed in order to close the breakers at the cogeneration plant, should the need arise. This was achieved via a dual fiber optic link with full synchronizing capabilities through the SEL-311 Series Relays.
"Connie Belonogoff, our relay technician, as well as Mark Hickenbottom and Bob Twoddle, our power system electricians, decided that we would connect the cogen unit at a different location on the bus, so that it would have improved 'switchability' for maintenance purposes," Briscombe explains. "Also we isolated the substation with the PG&E lines, so that faults will no longer go all the way through and trip the breakers at the cogeneration plant. In the past such a fault could darken the whole campus for a period, even though the line from PG&E would be hot. So now we have 'island' capabilities by virtue of the protected cogeneration system."
The primary task for Phase Two of the substation upgrade was to modernize the control panels, replacing the relays. "We decided to build a new control panel and cut the circuits over one at a time," Lewis says. "I wanted to use SEL relays to do the job, but the Stanford engineers were somewhat resistant to that idea. So, I persuaded them to go to one of the SEL seminars that are held in the area. They came back from the meeting just absolutely sold. That seminar addressed every misgiving that the Stanford people could've thought of, and then some. They came back ready to go with SEL as the product and supplier of choice."
"If you have a project like this, with more than 10 relays, you also need excellent support," Briscombe adds. "To coordinate that many relays, which are segregated in the bus, and have the ability to see faults in different directions and all sorts of similar complications, I believe you have to have SEL or a company like it to commission the project efficiently."
Glyn Lewis agrees on the importance of support. "There's a lot more to power system solutions than just employing the right technologies. It is how you deploy the technologies and support them that is important in the end." SEL relays were written into the supply specifications as "NO EQUAL" when the control panel was bid to several different manufacturers. In addition, SEL was made responsible for the complex programming of the SELogic and training of the Stanford personnel. Mike Thompson of the SSD provided phenomenal support during the factory testing and final commissioning of the system.
To that end Schweitzer's Systems and Services Division (SSD) provided extensive customer training, settings, commissioning support and other assistance. SSD designed a sophisticated directional comparison bus protection scheme that properly selects and trips zones based on the bus switching configuration. SSD provided customized documentation including bus protection schematics and graphical representation of the programming logic. SSD also supported the Stanford utility group in meetings with PG&E, assisted in the initial energization tests, and assisted with change orders to cover additional work. Finally, SSD was tasked with providing commissioning support in the spring of 2004 when the co-generation circuit is converted over to the new control system. This will finally allow islanding and remote control of the PG&E tie breakers from the co-gen.
"We've always wanted someone to come up with a description of how this place operates," Briscombe says. "Because SEL SSD is fully familiar with it, after doing the commissioning, we issued a supplemental contract to come up with the operating procedure for the entire system. They did an admirable job of that, too. It was exactly what we wanted."
Because Schweitzer's SSD "wrote the book" on the current Stanford power system, various members of the campus utility group have a better understanding of how the system is configured and controlled, so that they are able to operate as efficiently as possible and anticipate the needs of the future.
About Schweitzer Engineering Laboratories: SEL has been making electric power safer, more reliable and more economical since 1984. This ISO 9001-certified company serves the electric power industry worldwide through the design, manufacture, supply and support of products and services for power system protection, control, and monitoring. SEL Systems and Services Division assists in the application and use of products as well as providing complete systems customized for the specific application. From simple relay settings to substation automation systems to turnkey substation control houses, SEL SSD will add important value to your projects. For more information, contact SEL by phone (509) 332-1890; fax (509) 332-7990; or mail to 2350 NE Hopkins Court, Pullman, Wash 99163-5603. SEL is online at www.selinc.com.
Would you like information like this delivered to your email inbox? Subscribe to Tradeline Updates to keep abreast of the latest conference developments, industry news, best practices and more!