 Life Science Center

The four-story building was reprogrammed to keep as much as the existing structure in tact as possible. Larger departments, like Chemistry and Biology were relocated to the new 60,000-sf addition, while smaller departments were centralized to improve efficiencies. In addition to the Chemistry and Biology departments, the Life Sciences building houses an animal research laboratory; Physics; Geology; Engineering; Math and Statistics; Economics and Business; Nursing, and Elementary Education.

The replacement and improvement of the building's mechanical and electrical systems were a significant component of the project. A high velocity exhaust system was utilized in conjunction with minimum height stacks in order to protect a large telescope on the roof. By implementing both scenarios, the hot air exhaust came out fast and was dispersed over a large area quickly. Numerous fume hoods were installed to accommodate the teaching laboratories within the Chemistry Department.

All interior and exterior spaces are in compliance with ADA requirements and the College's Building Design Standards.




Project Information
Building Owner: Calvin College
Owner Contact: Gaylen Byker
Building Location: Grand Rapids, MI UNITED STATES
Project Type: Expansion
Principal Building Function: Academic, research
Project Timeline
Mar 1997Planning Start
Jul 1997Design Start
May 1998Construction Start
Aug 1999Completion
Last known status: Completed
Project Cost: $22,000,000
Construction Cost: $13,500,000
Cost Per Sq. Ft: $186
About These Cost Figures
Building Information
Project Includes: Biology
Chemistry
Education: Classroom
Laboratory: Teaching
Vivarium
Total GSF: 72,377
Total NSF: 49,231
Efficiency: 68%
Building Population: 1200
People Density: 60 gsf/person
Building Services: DI, H2, Oz, air, vacuum
Office Size: 10' x 11' NSF
Power Req: 20 w/nsf
Structure/Foundation: Concrete waffle slab, concrete columns, concrete spread footings
Laboratory Parameters
Lab Module: 20' x 30'
Casework Mat'l: Wood casework with resin tops
Fume Hoods: 53 @ 4' single hood to 8' walk-in hood
Project Team
Architect URS Corporation
Consultant - Laboratory Planner Research Facilities Design (RFD)
Engineer URS Corporation
Profile Created 03/31/2001
Last Updated 04/04/2006
About the Reported Cost Figures
The cost figures reported are supplied by the firms that submitted these projects for publication, which in most cases are the designers or builders. Whereas these sources are intimately familiar with their projects, they may not be fully aware of the owners' finally-realized and recorded costs. In some cases, costs are truly and completely accounted for, and in others they represent a near approximation of the final costs. Costs have not been adjusted for year of construction, nor has any attempt been made to make regional cost adjustments.

Further, costs are not comparable on any kind of detailed standard costing model. Hence, it is possible for the cost of one building to include a steam boiler, while the cost of a comparable building might not include the boiler, if steam is being supplied from an already existing campus grid. Or, in another case, a building might include excess boiler capacity to supply steam to another building. Some submittals include fees or unusual site improvements as part of the construction costs, which others do not.
We welcome your Questions and Comments

Copyright 2008 Tradeline Inc.
All Rights Reserved
ISSN: 1096-4894
Fig. 1

Life Science Center

 

 Related Resources

  Get Updates by Email
Would you like information like this delivered to your email inbox? Subscribe to Tradeline Updates to keep abreast of the latest conference developments, industry news, best practices and more!
Sign Up Now!