Prior to construction, three buildings had to be demolished. The site was severely constrained and situated on a very busy block. The foundations were excavated to approximately 30 feet tight against the street and adjacent structures. Numerous existing, vital utilities had to be relocated both temporarily and permanently as part of the project. The relocation involved installation of 2000 lineal feet of 4- to 5-foot trenching, installation of manholes, and associated duct bank without disruption to existing utility services to the area.
The height of the water table, approximately 24 feet above the basement slab elevation at the high point, presented a challenge for the structural design of the basement slab system. A continuously operational pump under-drain system was installed. However, if the pump were to fail, the basement slab is designed to allow water to enter the basement through covered slab openings to avoid significant heaving of the floor slab.
The building includes a three-story administration and EM/MRI wing and an L-shaped five-story neuroscience and molecular cell biology wing. Offices run on the perimeter of the building, separated by a connecting corridor to the lab support spaces, which are adjacent to labs on the opposite perimeter of the building. The facility houses classrooms and meeting spaces, with front projection video, microphones, video sources, data inputs, and video conferencing. The two wings are connected with a two-story bridge at the second and third floors. In addition, the Life Science building is connected to two existing buildings via an aerial bridge and first floor corridor.
By creating a set of lab blocks within building cores, the space is more adaptable to reconfiguration to future needs. This approach also creates a modular lab unit that is typical throughout the building. Each lab will be provided with plumbing and process utilities and with natural gas, compressed air, and vacuum at each bench. Local cylinders, as required, provide gases to lab spaces. Support and non-laboratory spaces are located outside the lab block to avoid conflicts of use and/or configuration. To minimize and control noise and vibration above and below mechanical areas, thicker than normal floor slabs were utilized. Two 11.2 kV electrical feeders feed power to the building, routed via separate underground paths for redundancy and reliability. An integrated building control system oversees security/card access, fire alarm/life safety, lighting, power monitoring, building automation, and laboratory controls.
Throughout pre-construction, the design phase team charted an environmentally responsible approach to the design and engineering of the building. Using the LEED checklist as a framework, the team incorporated several sustainable design elements such as a high performance envelope (Low-E coatings and daylighting), VAV laboratory control system, and user control of window treatments.
| Project Information | ||||||||||||
| Building Owner: | Brown University | |||||||||||
| Building Location: | Providence, Rhode Island UNITED STATES | |||||||||||
| Project Type: | New Construction | |||||||||||
| Principal Building Function: | Research and teaching facility | |||||||||||
| Project Delivery Method: | Construction Management | |||||||||||
| Project Timeline |
|
|||||||||||
| Project Cost: | $67,000,000 | |||||||||||
| Construction Cost: | $52,500,000 | |||||||||||
| Cost Per Sq. Ft: | $394 | |||||||||||
| About These Cost Figures | ||||||||||||
| Building Information | ||||||||||||
| Project Includes: |
Education Laboratory Life Sciences Research |
|||||||||||
| Total GSF: | 170,000 | |||||||||||
| Project Team | ||||||||||||
| Architect | Ballinger | |||||||||||
| Builder | Gilbane Building Company | |||||||||||
| Consultant - Laboratory Planner | GPR Planners Collaborative, Inc. | |||||||||||
| Engineer - Electrical | E.W. Audet & Sons Inc. | |||||||||||
| Engineer - Mechanical | Arden Engineering Constructors LLC | |||||||||||
| Supplier - Concrete | J.L. Marshall & Sons Inc. | |||||||||||
| Supplier - Flooring | Allegheny Contract Flooring | |||||||||||
| Supplier - Glass Block | Ipswich Bay Glass Co. | |||||||||||
| Supplier - Laboratory Controls | Environmental Growth Chambers | |||||||||||
| Supplier - Laboratory Equipment | Gibson Associates Inc. | |||||||||||
| Supplier - Masonry | Grande Masonry | |||||||||||
| Supplier - Precast | Lymo Construction Inc. | |||||||||||
| Supplier - Roofing | Apollo Roofing and Sheet Metal Inc. | |||||||||||
| Profile Created 05/28/2008 | ||||||||||||
| Last Updated 09/02/2008 | ||||||||||||
|
||||||||||||
Copyright 2008 Tradeline Inc.
All Rights Reserved
ISSN: 1096-4894
Lab Interior
Lobby

Printer Friendly Version
Send to a Friend
Complete Story