 Manufacturing & System Technology (M&ST) Facility

The 296,000 sf facility is subdivided into 60 percent high-bay for prototype equipment assembly and operation, and 40 percent low-bay for design engineer offices, training rooms and support. Meeting, huddle, common, and training spaces make up 30 percent of the low bay functions.  

The pre-engineered pre-cast structure is a long span steel frame for maximum flexibility to shrink or enlarge equipment prototypes and office functions.  All offices are open, and are sized per the P&G 8¢ by 8¢ standard, and grouped for communication efficiency. Pathways are shaped for team identification and "wayfinding" ease.  

High bay manufacturing space is "bare bones" quality with exposed large utility runs for convenient tap-in.  Office/training space is finished with medium grade materials including carpet, tile, drywall or masonry partitions and walls, lay-in acoustic ceiling, and lay-in fluorescent lighting.  Personnel and visitor entries and common areas were given special shape and finishing treatments.  

BHDP provided full architectural service from feasibility study of options through start-up.  All P&G goals for the space and project were exceeded.




Project Information
Building Owner: The Procter & Gamble Company
Owner Contact: Robert Wipperman, Associate Director, Corporate Facilities Engineering
Building Location: Cincinnati, OH UNITED STATES
Project Type: New Construction,Renovation
Principal Building Function: Manufacturing process development with related labs and offices
Project Delivery Method: Construction Management
Project Timeline
Aug 1998Planning Start
Nov 1998Design Start
Jun 1999Construction Start
Nov 1999Completion
Last known status: Completed
Cost Per Sq. Ft: $54
About These Cost Figures
Building Information
Project Includes: Conference Room
Laboratory: R&D
Manufacturing
Office: Researcher
R&D
Support
Training Room
Total GSF: 296,000
Total NSF: 246,000
Efficiency: 83%
Building Population: 409
People Density: 723 gsf/person
Building Services: Conventional M&E, fire protection, voice and data communications, central compressed air
Special Equip: 2 Large Steam Boilers
Office Size: 8' x 8' NSF
Power Req: 15 watts/sf
Laboratory Parameters
Lab Module: 11' x 22'
Casework Mat'l: Metal cabinets with laminate plastic tops
Fume Hoods: 20
Project Team
Architect BHDP Architecture
Builder Hunt Construction Group
Supplier - Furniture Haworth Inc.
Profile Created 04/17/2002
Last Updated 04/04/2006
About the Reported Cost Figures
The cost figures reported are supplied by the firms that submitted these projects for publication, which in most cases are the designers or builders. Whereas these sources are intimately familiar with their projects, they may not be fully aware of the owners' finally-realized and recorded costs. In some cases, costs are truly and completely accounted for, and in others they represent a near approximation of the final costs. Costs have not been adjusted for year of construction, nor has any attempt been made to make regional cost adjustments.

Further, costs are not comparable on any kind of detailed standard costing model. Hence, it is possible for the cost of one building to include a steam boiler, while the cost of a comparable building might not include the boiler, if steam is being supplied from an already existing campus grid. Or, in another case, a building might include excess boiler capacity to supply steam to another building. Some submittals include fees or unusual site improvements as part of the construction costs, which others do not.
We welcome your Questions and Comments

Copyright 2008 Tradeline Inc.
All Rights Reserved
ISSN: 1096-4894

 Related Resources

  Get Updates by Email
Would you like information like this delivered to your email inbox? Subscribe to Tradeline Updates to keep abreast of the latest conference developments, industry news, best practices and more!
Sign Up Now!