| Building Owner: |
 |
City of Worcester |
 |
|
Building Location:
|
|
Worcester, MA USA
|
 |
|
Project Type:
|
|
New Construction
|
 |
|
Principal Building Function:
|
|
convention center with exhibit hall and administrative space, meeting rooms and food service |
 |
|
Project Delivery Method:
|
|
Construction Management (CM)
|
 |
|
Project Timeline
|
|
| Jan 1996 | Completion |
|
Last known status: Completed
|
|
 |
| Construction Cost: |
|
$25,000,000 |
|
|
About These Cost Figures
|
 |
|
Project Includes:
|
|
Conference Room
|
| Total GSF: |
|
196,000 |
 |
 |
|
Architect
|
|
Perry Dean Rogers & Partners
|
 |
|
Architect
|
|
Thompson Ventulett Stainback & Associates Inc.
|
 |
|
Construction Management
|
|
Gilbane Building Company
|
 |
|
Construction Management
|
|
Cutler Associates
|
 |
 |
 |
| Profile Created 01/01/1996 |
| Last Updated 04/04/2006 |
 |
 |
The cost figures reported are supplied by the firms that submitted these
projects for publication, which in most cases are the designers or builders.
Whereas these sources are intimately familiar with their projects, they may
not be fully aware of the owners' finally-realized and recorded costs. In some
cases, costs are truly and completely accounted for, and in others they represent
a near approximation of the final costs. Costs have not been adjusted for
year of construction, nor has any attempt been made to make regional cost
adjustments.
Further, costs are not comparable on any kind of detailed standard costing model.
Hence, it is possible for the cost of one building to include a steam boiler, while
the cost of a comparable building might not include the boiler, if steam is being
supplied from an already existing campus grid. Or, in another case, a building might
include excess boiler capacity to supply steam to another building. Some submittals
include fees or unusual site improvements as part of the construction costs, which
others do not.
|
|
We welcome your
Questions and Comments
Copyright 2008 Tradeline Inc.
All Rights Reserved
ISSN: 1096-4894