Tradeline, Inc. | Leading-edge resources for facilities planning and management www.tradelineinc.com

Divisional Headquarters


Published January 1996

Project Information
Building Owner: Bayer Corporation
Building Location: West Haven, CT USA
Project Type: New Construction
Principal Building Function: Corporate Headquarters
Project Delivery Method: Construction Management (CM)
Project Timeline
Jan 1996Completion
Last known status: Completed
Building Information
Project Includes: Headquarters
Office
Total GSF: 250,000
Project Team
Architect Flad Architects
Contractor Gilbane Building Company
Engineer Affiliated Engineers Inc. (AEI)
Profile Created 01/01/1996
Last Updated 04/04/2006
Circulate to:

[ ]

[ ]

[ ]

Notes:














Copyright 2008 Tradeline Inc.
All Rights Reserved
ISSN: 1096-4894