Chiron Corporation, a biotechnology company, as recently made the commitment to redevelop its 2.2 million-sf campus. The concept is based on the corporation's response to its urban context, and is inspired by the plan of traditional Mexican cloisters. A series of atria, patios, plazas and open spaces are organized around working spaces. The spaces, each one unique, interconnect with one another, creating a large multi-level campus of research "villages" that support communication and collaboration among employees.
Phase I of the 30-year development plan began in 1999, and includes a 260,000-sf lab building and central utility plant. The laboratory incorporates a philosophy of business group integration. The first level of high-bay space includes building mechanicals, specialized lab space and offices, allowing business groups to support the efforts of researchers. The next three levels include labs designed to maximize exterior light, as well as flexibility to adapt to the diverse needs of business groups. These labs are located around interior courtyards and atria to facilitate interaction, demonstrating the owner's commitment to the social aspects of science as well as the technical.
Laboratory types include microbiology, biochemistry, chemistry, bio-organic/biophysics, robotics and support, including tissue culture, nuclear magnetic resonance, and isotope. The BSL-3 suite is designed to be flexible enough to accommodate a variety of types and uses of BSL-3 level pathogens and is designed for both bacterial and viral work.
Chiron’s Life Sciences building received R&D Magazine’s Lab of the Year award in 1999.
| Building Owner: |
 |
Chiron Corporation |
 |
|
Building Location:
|
|
Emeryville, CA UNITED STATES
|
 |
|
Project Type:
|
|
New Construction
|
 |
|
Principal Building Function:
|
|
Biotechnology research |
 |
|
Project Delivery Method:
|
|
Fast Track
|
 |
|
Project Timeline
|
|
| Oct 1994 | Planning Start |
| Oct 1994 | Design Start |
| Sep 1996 | Construction Start |
| Jun 1998 | Completion |
|
Last known status: Completed
|
|
 |
| Construction Cost: |
|
$102,000,000 |
| Cost Per Sq. Ft: |
|
$358 |
|
|
About These Cost Figures
|
 |
|
Project Includes:
|
|
Atrium
Biochemistry
Biocontainment
Biotechnology
Chemistry
Interdisciplinary Research
Laboratory
Nuclear Magnetic Resonance
Office
Pharmacology
|
| Total GSF: |
|
285,000 |
 |
 |
|
Architect
|
|
Flad Architects
|
 |
 |
|
Engineer - MEP
|
|
Affiliated Engineers Inc. (AEI)
|
 |
|
Laboratory Planner
|
|
Flad Architects
|
 |
 |
 |
| Profile Created 02/02/2007 |
| Last Updated 10/12/2007 |
 |
 |
The cost figures reported are supplied by the firms that submitted these
projects for publication, which in most cases are the designers or builders.
Whereas these sources are intimately familiar with their projects, they may
not be fully aware of the owners' finally-realized and recorded costs. In some
cases, costs are truly and completely accounted for, and in others they represent
a near approximation of the final costs. Costs have not been adjusted for
year of construction, nor has any attempt been made to make regional cost
adjustments.
Further, costs are not comparable on any kind of detailed standard costing model.
Hence, it is possible for the cost of one building to include a steam boiler, while
the cost of a comparable building might not include the boiler, if steam is being
supplied from an already existing campus grid. Or, in another case, a building might
include excess boiler capacity to supply steam to another building. Some submittals
include fees or unusual site improvements as part of the construction costs, which
others do not.
|
|