The design of the building separates vibration-sensitive micro fabrication laboratories (located in one wing) from vibration-producing civil and mechanical engineering laboratories (located in the opposite wing). Department and faculty offices are located in the bridge element between both wings to promote interaction and future flexibility for faculty allocation as programs expand or contract. The facility integrates the smaller existing award-winning Engineering Research Building by giving it pre-eminence in the palm tree-lined quadrangle.
The building exterior is a combination of painted poured-in-place concrete with tile trim. The bridge building is lined with tile panels on a steel frame. The principal interior spaces are organized around a main lobby in the east wing with views toward the new quadrangle and a series of interactive spaces located at corridor ends, terraces and balconies.
| Project Information | ||||||||||||
| Building Owner: | University of California, Irvine | |||||||||||
| Owner Contact: | Laurel Wilkening, Chancellor | |||||||||||
| Building Location: | Irvine, CA UNITED STATES | |||||||||||
| Project Type: | New Construction | |||||||||||
| Principal Building Function: | Research and Teaching | |||||||||||
| Project Delivery Method: | Bid | |||||||||||
| Project Timeline |
|
|||||||||||
| Construction Cost: | $24,756,049 | |||||||||||
| Cost Per Sq. Ft: | $185 | |||||||||||
| About These Cost Figures | ||||||||||||
| Building Information | ||||||||||||
| Project Includes: |
Education Education: Administration Education: Classroom Education: Faculty Office Engineering Laboratory: Research Laboratory: Teaching |
|||||||||||
| Total GSF: | 133,790 | |||||||||||
| Total NSF: | 74,005 | |||||||||||
| Efficiency: | 55% | |||||||||||
| Building Population: | 250 | |||||||||||
| Building Services: | Domestic and industrial hot and cold water, process cooling, Di, compressed air, natural gas, vacuum, emergency power, telephone/data | |||||||||||
| Special Equip: | Class 100, 1000 and 10,000 cleanrooms | |||||||||||
| Office Size: | 132 NSF | |||||||||||
| Power Req: | Lighting 290 KVA; lab equipment 800 KVA; mechanical power 775 KVA | |||||||||||
| HVAC Req: | Laboratory: 2.5 cfm/nsf, cleanroom: 4.5 cfm/nsf, Offices, VAV recirculating system: 6 air changes/hr | |||||||||||
| Structure/Foundation: | Exposed architectural concrete and steel frame with exterior stud/tile walls or cement plaster finish | |||||||||||
| Laboratory Parameters | ||||||||||||
| Lab Module: | 11' x 30' | |||||||||||
| Casework Mat'l: | C-frame base cabinets in cleanroom, standard floor-mounted base cabinets | |||||||||||
| Fume Hoods: | Constant volume fume hoods, laminar-flow fume hoods | |||||||||||
| Project Team | ||||||||||||
| Architect | Zimmer Gunsul Frasca Architects LLP | |||||||||||
| Builder | McCarthy Building Companies Inc. | |||||||||||
| Consultant - Electrical | Frederick Brown Associates | |||||||||||
| Consultant - Laboratory Planner | Earl Walls Associates | |||||||||||
| Consultant - Mechanical | Tsuchiyama & Kaino | |||||||||||
| Consultant - Structural | KPFF Consulting Engineers | |||||||||||
| Supplier - Fume Hoods | ISEC Inc. | |||||||||||
| Supplier - Fume Hoods | Fisher Hamilton | |||||||||||
| Supplier - Fume Hoods | NUAIRE Inc. | |||||||||||
| Profile Created 02/01/1994 | ||||||||||||
| Last Updated 04/04/2006 | ||||||||||||
|
||||||||||||
Copyright 2008 Tradeline Inc.
All Rights Reserved
ISSN: 1096-4894
Exterior A
Exterior B
Floorplan

Printer Friendly Version
Send to a Friend
Complete Story