Southeast Campus Chilled Water Plant
Occupancy: 1997
Published January 1996
The University of Florida's Brain Institute and Shands Teaching Hospital are accommodated by the Southeast Campus Chilled Water Plant, electrical services, domestic water and sanitary sewer service.
The chilled water system build-out holds 4,800 tons with future expandable capacity to 9,600 tons. The initial build-out includee four 1,200-ton high-efficiency hermetic electric centrifugal water chillers using R-1 23 refrigerant, constant volume primary pumps, variable volume secondary pumps, two expansion tanks and 24' of underground distribution piping. The system is provided with a chilled water optimization control capable of maintaining up to eight chillers and their associated auxiliary equipment, including cooling towers. The electrical system initial build-out included 22.9 KV primary selective fused switches, 22.9 KV to 5 KV transformation, 5 KV vacuum circuit breaker switchgears, and 5 KV to 480 volt transformation.
Also included is a domestic water system, a fire protection system and sanitary sewer distribution system. Distribution systems are routed through an underground utility corridor. Infrastructure services are designed to facilitate expansion to accommodate connection to the Brain Institute.
| Building Owner: |
 |
University of Florida |
 |
|
Owner Contact:
|
|
Joseph A. Kurinec, Project Manager
|
 |
|
Building Location:
|
|
Gainesville, FL UNITED STATES
|
 |
|
Project Type:
|
|
New Construction
|
 |
|
Principal Building Function:
|
|
Chilled Water Plant |
 |
|
Project Delivery Method:
|
|
General Contractor
|
 |
|
Project Timeline
|
|
| Jan 1995 | Planning Start |
| Apr 1995 | Design Start |
| Jan 1996 | Construction Start |
| Jan 1996 | Completion |
|
Last known status: Completed
|
|
 |
| Project Cost: |
|
$11,400,000 |
| Construction Cost: |
|
$10,800,000 |
|
|
About These Cost Figures
|
 |
|
Project Includes:
|
|
Education
Utility Plant
|
| Total GSF: |
|
12,700 |
 |
|
Special Equip:
|
|
HVAC - 2: 1200-ton chillers
4: 2400 gpm primary pumps
2: 200hp distribution pumps pumping 10,000 gpm through distribution loop approximately 8,000 feet, steel pipe ranging from 30-inch to 24-inch to 2-inch diameter, CHW distributed in urban area requiring extensive utility service re-routing
Electrical: 23 K/V substation
|
 |
|
Architect
|
|
Flad Architects
|
 |
 |
 |
|
Consultant - Engineer
|
|
Affiliated Engineers Inc. (AEI)
|
 |
 |
 |
 |
 |
 |
 |
| Profile Created 01/01/1996 |
| Last Updated 04/04/2006 |
 |
 |
The cost figures reported are supplied by the firms that submitted these
projects for publication, which in most cases are the designers or builders.
Whereas these sources are intimately familiar with their projects, they may
not be fully aware of the owners' finally-realized and recorded costs. In some
cases, costs are truly and completely accounted for, and in others they represent
a near approximation of the final costs. Costs have not been adjusted for
year of construction, nor has any attempt been made to make regional cost
adjustments.
Further, costs are not comparable on any kind of detailed standard costing model.
Hence, it is possible for the cost of one building to include a steam boiler, while
the cost of a comparable building might not include the boiler, if steam is being
supplied from an already existing campus grid. Or, in another case, a building might
include excess boiler capacity to supply steam to another building. Some submittals
include fees or unusual site improvements as part of the construction costs, which
others do not.
|
|
|
Circulate to:
[ ]
[ ]
[ ]
Notes:
|